Readiness of the building for implementation
Procedure
How to prepare for a smooth implementation?
Just follow the steps below. If you follow them, you won’t experience unnecessary delays that cost you money.
- Water (potable or according to ČSN 732028), minimum constant pressure of 250 kPa, temperature max. 30 °C, stable supply without interruption of supply, e.g. with a ¾ inch ball valve.
- Electricity supply, i.e. at least one (1) 380 V/32 A electrical socket, 25B circuit breaker, connected and fully operational on the basis of a valid electrical inspection, stable supply without interruption of supply. If SILA is used, a 32C main circuit breaker is required.
- Completely enclosed building in winter and substrate temperature min. +5°C (that is air temperature approx. +10°C).
- The substrate for plastering must be dry (brick, masonry, plaster: < 3%, aerated concrete: < 4%).
- The electrical boxes must be offset from the existing masonry by a maximum of 8 mm in the plane.
- All electrical, water and waste pipes must be buried.
- Treat metal parts with primer, or recoat with adhesive, and glass with fibre cloth (perlinka).
- Clean the PUR foam around the hole fillers and, if vapour barrier tape is used, glue it to the substrate (joist, lintel, sill).
- Cover the wiring on the floors in places where there will be more movement of workers when transporting material to the machine (corridors).
- Cleared building
- Paved access road to the site for smooth access of a vehicle with hydraulic arm (approx. 25 tons) or a vehicle for the delivery and supply of silos.
- Locked and secured areas for storage of tools and materials so that theft/damage cannot occur without overcoming an obstruction.